Haynes pipeline delay and Seal Beach franchise dispute
Long Beach
Summary
Construction began in May to supply recycled water to LADWP's Haynes Generating Station, which must stop using ocean water for cooling by 2029. The plant could use up to a third of the city's recycled water, prompting exploration of additional supply from the Los Coyotes reclamation plant.
At a glance
- Total mentions
- 2
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Oct 15, 2026.
Impact analysis
About $13 million of the $20 million contract covers the postponed segment; delays shift $8–10 million (water) and $3 million (sewer) in projected spending.
The city gains a major recycled water customer and reduces reliance on ocean cooling that harms marine life.
Without a Seal Beach franchise agreement, recycled water expansion stalls and potable water gets used where recycled water could suffice.
Mentions & discussions (2)
Utilities Commission Infrastructure Committee - Oct 15, 2026
A key segment of the $20 million LADWP Haynes pipeline — including a bore under the 22 freeway — is postponed until LA County repairs the College Drive Bridge. If no franchise agreement with Seal Beach is reached, that pipeline segment could become a dead end, forcing Haynes to take potable water instead of recycled water.
Climate Resilient and Sustainable City Commission - Jun 25, 2026
Construction began in May to supply recycled water to LADWP's Haynes Generating Station, which must stop using ocean water for cooling by 2029. The plant could use up to a third of the city's recycled water, prompting exploration of additional supply from the Los Coyotes reclamation plant.
We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.
The weekly brief for Long Beach
What the council decided, in plain English — one email a week.
Free. Unsubscribe with one click any time. We never sell your email.