LADWP Haynes Generating Station pipeline improvements
Long Beach
Summary
Long Beach is managing recycled water, sewer, and now potable water pipeline projects to serve the Haynes power plant as it phases out ocean cooling by 2029. LADWP pays all costs, and the work could create recycled water connections for future city customers.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Last discussed Jun 18, 2026.
Impact analysis
Contract grew by $10 million to $70 million, but LADWP reimburses the city for everything.
Residents get regional environmental benefits and potential future recycled water connections, at no cost to ratepayers.